Interconnector

Australia (SA) – Australia (VI) interconnection

Australia

6th-largest interconnector in Australia of 9 · top 51% worldwide (#356 of 704)

Status
operating
Capacity
820 MW
Length
654 km
Voltage
500 kV
Connects to
Australia
Reverse capacity
700 MW
Geometry
Schematic — node to node, not a surveyed route

Comparable interconnectors · Australia · 9 ranked

All interconnectors in Australia

Co-located infrastructure · within 25 km

On the interactive map

Open the interactive map →

For planned capacity it is assumed that 'Option 1' of the identified AEMO transmission expansion options will be realised. A 'Long' lead time equals 7 years post final publication year (2024) hence assumed 2031 as commissioning year.