Data Centre

CenturyLink

Operator
Lumen Technologies
Status
operating

Grid connection · within 50 km

Nearest substation
Chuck Lenzie Substation
Its voltage
500 kV
Distance
30 km
Strongest line nearby
500 kV
Line operator
Nevada Power Company
Substations in range
9

Mapped grid infrastructure from OpenStreetMap, whose coverage is excellent in some regions and sparse in others. Nothing shown here means nothing is mappednearby — not that the site is unconnected. Lines are matched on a segment’s midpoint, so a corridor passing directly overhead can be missed; this under-reports rather than invents.

Co-located infrastructure · within 25 km

On the interactive map

Open the interactive map →

Portfolio

SOURCE: OpenStreetMap (ODbL) © OpenStreetMap contributors