Interconnector

United States (US-CAL-CISO) – United States (US-NW-NEVP) interconnection

United States

33rd-largest interconnector in United States of 159 · top 33% worldwide (#227 of 704)

Status
operating
Capacity
1,401 MW
Length
660 km
Connects to
United States
Reverse capacity
296 MW
Geometry
Schematic — node to node, not a surveyed route

Comparable interconnectors · United States · 159 ranked

All interconnectors in United States

Co-located infrastructure · within 25 km

On the interactive map

Open the interactive map →

Assumption that the max hourly interchange value reached between Jan 2019 - Dec 2023 is representative for available transmission capacity between BA's. Distance for planned capacity is converted from miles into km. — This corresponds to the Nevada Power Company to the Southern California Edison (CAISO) Section of the TransWest Express transmission project.

SOURCE: Global Transmission Database v0.1 (CC BY 4.0)