Browse the atlas
OverWatts AtlasCountriesOwnersInsightsWireChangesSources Live map
Asset classes
- Transmission Line80,968
- Power Plant32,429
- Substation / Converter7,614
- Oil & Gas Field7,055
- Coal / Uranium Mine5,382
- Pipeline4,951
- Cement Plant3,513
- Data Centre3,283
- Iron & Steel Plant1,293
- LNG Terminal1,198
- Grid Storage965
- Iron Ore Mine949
- Chemical Plant868
- Interconnector704
- Export Terminal519
- Refinery279
- Storage / Tank Farm38
- Oil / Commodity Contract19
- Hydrogen Project18
- Carbon Capture (CCS)16
Chokepoints
Pipeline
Etrez-Vernier Gas Pipeline
France, Switzerland
- Operator
- NaTran, Gaznat
- Status
- operating
- Commissioned
- 1989
- Length
- 73.11 km
- Commodity
- gas
Co-located infrastructure · within 25 km
- 380 kV line2.1 km · Transmission Line
- Poste électrique de Verbois2.1 km · Substation / Converter
- Verbois hydroelectric plant2.2 km · Power Plant · 103 MW · hydro
- Liaison 400 kV n°1 Bois-Tollot - Génissiat-poste3.2 km · Transmission Line
- 400 kV line4.3 km · Transmission Line
- Equinix GV27.9 km · Data Centre
- Poste électrique de Bois-Tollot8.1 km · Substation / Converter
- Poste électrique de Bois-de-Serves8.2 km · Substation / Converter
- GEN018.7 km · Data Centre
- Equinix GV111 km · Data Centre
- Annecy-La Gabiule Gas Pipeline18 km · Pipeline
- Genissiat hydroelectric plant21 km · Power Plant · 420 MW · hydro
On the interactive map
France → Switzerland
SOURCE: Global Energy Monitor · Global Gas & Oil/NGL Pipelines (GGIT / GOIT) (CC BY 4.0)